Perth 03/21 Runway Works
Posted: Tue Feb 02, 2010 6:06 pm
by Nafenn
RWY 03/21 NOT AVBL
DUE WIP
RWY 03/21 INSTR VISUAL APCH NOT AVBL
RWY 03/21 AVBL FOR TAXI BTN TWY DELTA 1 AND TWY KILO
TWY WHISKEY BTN RWY 03/21 AND TWY CHARLIE 1 NOT AVBL
TWY ALPHA 3 AND MIKE NOT AVBL
REF METHOD OF WORKING PLAN YPPH 005/09 STAGE 1
FROM 01 312330 TO 02 061100 EST
DAILY 2330/1100
Daily from 0730 to 1900WST (Except Sunday), 03/21 at Perth Intl is closed, so all aircraft will be taking off and landing off the "cross runway" 06/24.
Because of the location of runway - the approach path of 06/departure path of 24 will put aircraft fairly low over the Belmont/Cloverdale/Redcliffe area.
From 1900 - 0730 Daily, and Sundays, 03/21 will be open for normal opperation.
Re: Perth 03/21 Runway Works
Posted: Tue Feb 02, 2010 6:39 pm
by yorky
Nafenn wrote:Because of the location of runway - the approach path of 06/departure path of 24 will put aircraft fairly low over the Belmont/Cloverdale/Redcliffe area.
No kidding.
Compulsory plane spotting ahoy for me
Re: Perth 03/21 Runway Works
Posted: Tue Feb 02, 2010 7:55 pm
by Nafenn
yorky wrote:No kidding.
Compulsory plane spotting ahoy for me
i know the feeling, i can just sit in the back yard and take photos now
Re: Perth 03/21 Runway Works
Posted: Sun Feb 21, 2010 11:33 am
by Infernal
Runway works, stage 2, Northern end of the runway, from TWY N to THR, works completed between 07:00 and 19:00 no work on Sundays!!, RWY 03/21 closed to all traffic during those hours, all traffic routed via 06/24, stage one has been completed. ok??
Stage 4, the intersection, Works being completed between the hours of 00:25 and 05:00 no work Sunday Morning!!, full closure of airport to all fixed wing aircraft, currently under way now, due to finish friday.
Stage 3, Sothern section of runway from TWY P/J2 to RWY 03 THR, Works completed during the hours of 07:00 and 19:00, no work on Sundays!! RWY 03/21 closed to all traffic during those hours, all traffic routed via 06/24, Stage 3 has not been started.
Stage 5, will be some several months after, and is the Groving of Rwy 21/03